Ogden Infrastructure Relocation

Project Overview

The City of Calgary has requested ENMAX Power to relocate existing electrical utilities in conflict with the future Green Line LRT alignment. Removing these conflicts ensures the alignment will be ready for future Green Line construction in the Ogden area.

Work began in April 2020, with anticipated completion by early July 2020.

The project includes the following:

  • Removal of existing overhead distribution cable along 26A Street SE and line burial along 68 Avenue SE, 74 Avenue SE and Ogden Road SE
  • Installation of lateral ducts along underground alignment
  • Distribution cable, pole and anchor replacement
  • Modifications and installation of associated utility equipment (manholes, switching cubicles and padmount transformers)

Both civil and electrical work will impact the following roadways:

  • Ogden Road SE
  • Odgen Dale Road SE
  • 25 Street SE
  • 26A Street SE
  • 69 Avenue SE
  • 72 Avenue SE
  • 74 Avenue SE

Businesses and residents directly impacted by construction activities will be notified in advance by ENMAX Power Customer Relations team.

Ogden infastructure relocation

Civil construction will take place within the City-owned road allowance, which will include excavation along existing roadways, sidewalks, pathways and greenspaces. After work is complete, ground disturbance will be restored.

Please note, this work could produce various noise levels and minor vibrations during civil construction activities.

ENMAX Power and the City of Calgary are working to ensure the work plan maintains the flow of vehicle and pedestrian traffic. Accommodations will be in place to include fencing, proper signage and road plates along construction routes. Access to all residential and commercial buildings will be maintained throughout construction.

For more information about the Green Line, please call 311 or visit Calgary.ca/greenline.


Questions?

Email: Power Customer Relations
Phone: 403-514-3990


Project Schedule

Both civil and electrical work began early April 2020, with anticipated completion by early July 2020.


CONSTRUCTION
AREA
CONSTRUCTION
TIMELINE
DETAILS

 69 Avenue SE & Ogden Road SE intersection

Starting mid–April 2020 for approximately one month.
Temporary lane closures to accommodate installation of new manholes and associated underground infrastructure.
Ogden Dale Road SE (east of CP railway tracks, south of 69 Avenue SE)

Starting April 27, 2020 for approximately two weeks.

Temporary single lane closure to accommodate overhead and underground installations. Two-way traffic will be maintained.
74 Avenue SE

Targeting April 27, 2020.

Temporary single lane closure to accommodate line burial. Two–way traffic will be maintained.

Ogden Road SE

Targeting late May 2020.

Temporary single lane closure to accommodate line burial. Two–way traffic will be maintained.