Ogden Infrastructure Relocation

Project Overview

The City of Calgary has requested ENMAX Power to relocate existing electrical utilities in conflict with the future Green Line LRT alignment. Removing these conflicts ensures the alignment will be ready for major Green Line construction.

Utility work is scheduled to begin January 20, 2020 and will continue for approximately two months. Crews will be working primarily Monday to Friday from 7 a.m. until 5 p.m. To accommodate the underground crossing along CP railway tracks, crews will work Monday to Saturday from 7 am. Until 7 p.m. and Sunday from 9 a.m. until 7 p.m. (CP flagger dependent).

The project includes the following:

  • Modifications and upgrades to current electrical infrastructure
  • Installation of steel pipes and casings for underground cable
  • Replacement of some existing distribution poles
  • Installation of new manholes and underground connecting ducts
  • Rerouting of underground connections

The following locations will be impacted by construction activities, to include CP railway crossing:

  • Ogden Dale Road SE (vehicle detours in effect January 20 to February 9, 2020)
  • 74 Avenue SE
  • 26A Street SE, between 74 Avenue and 76 Avenue SE


Questions?

Email: Power Customer Relations
Phone: 403-514-3990

ENMAX Power and the City of Calgary are working to ensure the work plan maintains the flow of vehicle and pedestrian traffic. Accommodations will be in place to include fencing, proper signage and road plates along construction routes.

Please note, this work could produce various noise levels and minor vibrations during civil construction activities.

Access to all residential and commercial buildings will be maintained throughout construction. Remediation of boulevards and pathways will take place in Spring 2020 or earlier, pending weather conditions.

Businesses and residents directly impacted by construction activities will be notified in advance by ENMAX Power Customer Relations team.

For more information about the Green Line, please call 311 or visit Calgary.ca/greenline.


Project Schedule

Civil and electrical work will begin on January 20, 2020 and will continue for approximately two months.

CONSTRUCTION
AREA
CONSTRUCTION
TIMELINE
DETAILS

Ogden Dale Road SE

January 20 until February 9, 2020

Civil construction will involve trenchless crossing under CP railway tracks, to commence on Ogden Dale Road SE heading west towards 26A Street and 74 Avenue SE.
Laneway east of 26A Street SE

January 23, 2020 for approximately two weeks

Civil construction activities to include manhole installation in laneway east of 26A Street SE. Temporary laneway access closure at north end: south access maintained via 76 Avenue SE.
Roadway south of 74 Avenue SE

Starting late January, 2020

Civil construction activities to include open cut trenching and new distribution pole and anchor installation on south side of 74 Avenue SE. Curb lane and sidewalk closure in effect.


The highlighted area indicates the approximate work location of crews. 