Get Connected

This page is for electricians, developers and contractors requesting electrical services for projects within the ENMAX service area.

Have a question?

Email: getconnected@enmax.com
Phone: 403-514-3716

Use our interactive map to see if your project is within the ENMAX service area.

Check your location

Not in our Service Area? Find your service territory.

If your project is within the Calgary downtown core network, you may have some additional requirements. Please review the Network Services Policy Guidelines.

Let's get your project started

  To complete this form 

You will need to know the following information about your project: 

  • Service details including phase, amps and voltage (if you’re requesting a new service or service upgrade) 
  • Existing Service details (if you’re requesting a service upgrade) 
  • Site plan of your project. (This could be something as simple as a marked up google screenshot or as complex as a drafted drawing.) 
  • If you’re requesting a service size of 400A or greater we will also need to see an electrical single line diagram. 

  What's next

We will contact you within two working days after you submit your form.

Our team will review all documentation and compare it to the surrounding electrical grid to ensure existing infrastructure's ability to support your project.

From there, we’ll determine the next course of action which may include:

  • A rough timeline* of construction completion. 
  • Initial Payment** request so we can start working on design and engineering required to send you a detailed quote. 

* Timelines vary from Project to Project and do not start until Initial Payment is received. Timeline refers to construction of the facilities needed to bring you power. Secondary cable energization to your facilities are not included in this. See the energization process.

** The Initial Payment is required to cover cost to produce a preliminary design & formal quotation and will be deducted from the final quoted price. In the event of project cancellation, the customer will be refunded minus any incurred costs.