This project will occur for approximately ten (10) days.
Dates:
This work is anticipated to begin on November 12, 2025.
Locations:
This work will occur along 3 Avenue SW, between 1 Street SW and 2 Street SW.
Work Hours:
Weekdays; 7:00 a.m. – 7:00 p.m.
Weekend; 7:00 a.m. – 7:00 p.m.
Project maps
What to expect
We make every effort to minimize the effect our work has on daily activities, and we follow all applicable standards and bylaws. Below are the things to be aware of related to this project. .
During construction:
ENMAX Power and contractor vehicles and associated utility equipment will be on site.
Construction barricades and/or safety fencing.
Project and/or road signage.
Noise and/or minor vibrations during construction.
Traffic: Road closures, detours, parking, and access:
Road closure on 3 Avenue SW, between 1 Street SW and 2 Street SW (See Yellow zone on map on reverse). Please follow on-site signage and detours.
November 21 – 22, 2025:
Sidewalk closure on the south side of 3 Avenue SW, adjacent to 2 Street SW (See Red zone on map above). Pease follow traffic and detour signage.
Power outages:
A power outage is not required to facilitate this work.
After construction:
The work area will be remediated back to original state following the final completion of the project
Project support
Contact us
Call, email, or request a callback for questions or comments about this project.