Ramsay Infrastructure Relocation

Project Overview

The City of Calgary has requested ENMAX Power to relocate existing electrical utilities in conflict with the future Green Line LRT alignment. Removing these conflicts ensures the alignment will be ready for major Green Line construction.

Utility work will involve various stages within the Ramsay area. Work began in April 2019 and will continue into Q4 of 2020.

The project includes the following:

  • Modifications and upgrades to current electrical infrastructure
  • Installation of steel pipes and casings for underground cable
  • Replacement of some existing distribution poles
  • Installation of new manholes and underground connecting ducts
  • Rerouting of underground connections

The following locations will be impacted by construction activities, to include crossing at the adjacent CP railway tracks:

  • 12 Street SE and 17 Avenue SE
  • Blackfoot Trail SE and 15 Street SE
  • 34 Avenue SE and Ogden Road SE

ENMAX Power and the City of Calgary are working to ensure the work plan maintains the flow of vehicle and pedestrian traffic. Accommodations will be in place to include fencing, proper signage and road plates along construction routes.

Please note, this work could produce various noise levels and minor vibrations during civil construction activities.

Access to all residential and commercial buildings will be maintained throughout construction.

Businesses and residents directly impacted by construction activities will be notified in advance by ENMAX Power Customer Relations team.

For more information about the Green Line, please call 311 or visit Calgary.ca/greenline.

Questions?

Email: Power Customer Relations
Phone: 403-514-3990


Project Schedule

Both civil and electrical work began early April 2019 and will continue into early 2021 and will continue into late 2020.

CONSTRUCTION
AREA
CONSTRUCTION
TIMELINE
DETAILS

12 Street SE & 17 Avenue SE

24/7 operations until 5 p.m. on December 24, 2020. Intermittent day and night work from December 26 to 31, 2020. Work to resume on January 2, 2021.
Micro tunneling under CP railway tracks is complete. Remaining civil work includes cable installations and tying into new manholes.
Blackfoot Trail SE & 15 Street SE

Contractor and ENMAX crews will be on site until December 24, 2020. Work will resume December 27 to 20, 2020, and again on January 2, 2021.

Relocation of existing overhead distribution line to underground. Work will take place along 15 Street SE, between 8 Avenue SE and Alyth Road SE.
34 Avenue SE & Ogden Road SE

ON HOLD until early January 2021.

Pipe ramming underneath CN railway tracks, north of 34 Avenue SE, between 11 Street SE and Ogden Road SE.