​Ramsay Infrastructure Relocation

Project Overview

The City of Calgary has requested ENMAX Power to relocate existing electrical utilities in conflict with the future Green Line LRT alignment. Removing these conflicts ensures the alignment will be ready for major Green Line construction.

Utility work will involve various stages within the Ramsay area. Work began in April 2019 and will continue into Q2 of 2020. Crews will be working primarily Monday to Saturday from 7:00 a.m. until 7:00 p.m. and Sunday from 9 a.m. until 7 p.m. (CP flagger dependent).

The project includes the following:

  • Modifications and upgrades to current electrical infrastructure
  • Installation of steel pipes and casings for underground cable
  • Replacement of some existing distribution poles
  • Installation of new manholes and underground connecting ducts
  • Rerouting of underground connections

The following locations will be impacted by construction activities, to include CP railway crossing:

  • 12 Street SE and 17 Avenue SE
  • 11 Street SE and 20 Avenue SE
  • 11 Street SE and 21 Avenue SE


Questions?

Email: Power Customer Relations
Phone: 403-514-3990

ENMAX Power and the City of Calgary are working to ensure the work plan maintains the flow of vehicle and pedestrian traffic. Accommodations will be in place to include fencing, proper signage and road plates along construction routes.

Please note, this work could produce various noise levels and minor vibrations during civil construction activities.

Access to all residential and commercial buildings will be maintained throughout construction.

Businesses and residents directly impacted by construction activities will be notified in advance by ENMAX Power Customer Relations team.

For more information about the Green Line, please call 311 or visit Calgary.ca/greenline.


Project Schedule

Both civil and electrical work began early April 2019 with anticipated completion in Q1 of 2020.

CONSTRUCTION
AREA
CONSTRUCTION
TIMELINE
DETAILS

 12 Street SE & 17 Avenue SE

July 2019 to Q1 2020

Civil construction will involve trenchless crossing under CP railway tracks, to commence east of 12 Street SE toward 17 Avenue SE.

Civil construction activities in manhole located along 17 Avenue SE and 13 Street SE.
 11 Street & 20 Avenue SE

April 2019 to Q1 2020

Trenchless crossing under CP railway tracks to begin late January 2020.
11 Street & 21 Avenue SE

May 2019 to Q2 2020

Trenchless crossing under CP railway tracks to begin late January 2020.


The highlighted red area indicates the approximate work location of crews. 