ENMAX No.7 Substation Upgrades

Project Overview

ENMAX Power Corporation (ENMAX) is proposing to replace two 138-25kv 30 MVA transformers with two 30/40/50 MVA transformers and add a 138 kV circuit breaker at ENMAX No.7 Substation located in SW Calgary, to maintain restoration capability and accommodate load growth. The Substation is located at 718 – 101 Street SW, Calgary.

Please see the Alberta Electric System Operator (AESO) Need Overview document included in this project package for more information regarding the need for these substation upgrades.

Important Documents

Project status

ENMAX filed an application with the Alberta Utilities Commission (AUC) for the proposed work on October 23, 2017. The AUC issued a decision approving the project and new permits and licenses on November 22, 2017. Construction is scheduled to start in March 2018 with completion by December 2018.

Questions?

Email: Stakeholder Relations
Phone: 403-514-1471



All customers are free to purchase natural gas services from the default supply provider or from a retailer of their choice and to purchase electricity services from the regulated rate provider or from a retailer of their choice. The delivery of natural gas and electricity to you is not affected by your choice. If you change who you purchase natural gas services or electricity services from, you will continue receiving natural gas and electricity from the distribution company in your service area. For a current list of retailers you may choose from, visit www.ucahelps.alberta.ca or call 310-4822 (toll free in Alberta).