2. Expect Your Return Call, Usually Within the Same Business Day
The planner will walk you through what service is currently available and the process needed to fulfill your request. The planning process can take twelve weeks (and occasionally longer) outside the downtown area and a minimum of eight weeks inside downtown depending on the scope and location of the request.
3. An ENMAX Inspector & an Electrical Inspector May Need to Review Your Plans.
This step must be done prior to any installation.
4. Obtain Your Site ID
You now require a Site Identification number to secure an electrical installation in Alberta. To obtain the Site ID a form must be completed and submitted to ENMAX Power. To access the correct form click on the link below.
For each site, you'll need to provide the address, service type and characteristics (volts, amps, phases & wire count) and permit number.
In Calgary, for a single family homes and duplexes the building permit number is required. For condos, multi-family homes and commercial properties the electrical permit number is required.
For Red Deer all services require the electrical permit.